Painters are ahead of schedule

5 Nov 2018

Integrity has advised that Programmed are now ahead of schedule on Penthouse and Skyhome balconies, by approximately 2 weeks.

A revised schedule has been issued for circulation to the remaining Skyhome owner/occupiers:

Updated schedule as follows

  • 581/582/584/585/586/588                            5 to 9 November 2018
  • 583/561/562/563/564/565/566                     12 to 16 November 2018
  • 568/541/542/543/544/545/546                     19 to 23 November 2018
  • 548/521/522/523/524/525/526                     26 to 18 November 2018
  • 528 and various remaining apartments         3 to 7 December 2018
    (including wall colour and floor issues)
Skyhome Schedule 5Nov2018