Painters are ahead of schedule
5 Nov 2018
Integrity has advised that Programmed are now ahead of schedule on Penthouse and Skyhome balconies, by approximately 2 weeks.
A revised schedule has been issued for circulation to the remaining Skyhome owner/occupiers:
Updated schedule as follows
- 581/582/584/585/586/588 5 to 9 November 2018
- 583/561/562/563/564/565/566 12 to 16 November 2018
- 568/541/542/543/544/545/546 19 to 23 November 2018
- 548/521/522/523/524/525/526 26 to 18 November 2018
- 528 and various remaining apartments 3 to 7 December 2018
(including wall colour and floor issues)